KPlato/Manual/Project Performance View

Jump to: navigation, search

Description

The Project performance view is a project management chart where can be understood the actual situation of the project according the Earned Value Method.

Kplato project perf chart.png

where:

  • BCWS means Budgeted Cost Work Scheduled,
  • BCWP means Budgeted Cost Work Performed,
  • ACWP means Actual Cost Work Performed.

All these are considered as effort in hours and costs.

PI are the Performance Indexes, where:

  • CPI is the Cost Performance Index,
  • SPI is the Schedule Performance Index.

This page was last modified on 17 August 2012, at 16:41. Content is available under Creative Commons License SA 4.0 unless otherwise noted.