==Description==
 
==Description==
The Project performance view is a project management chart where can be understood the actual situation of the project according the Earned Value Method.
+
The Project performance view is a project management chart where can be understood the actual situation of the project according to the Earned Value Method.
  
 
[[Image:Plan_project_perf_chart.png|300px|thumb]]
 
[[Image:Plan_project_perf_chart.png|300px|thumb]]

Revision as of 10:29, 1 November 2019

Description

The Project performance view is a project management chart where can be understood the actual situation of the project according to the Earned Value Method.

Plan project perf chart.png

where:

  • BCWS means Budgeted Cost Work Scheduled,
  • BCWP means Budgeted Cost Work Performed,
  • ACWP means Actual Cost Work Performed.

All these are considered as effort in hours and costs.

PI are the Performance Indexes, where:

  • CPI is the Cost Performance Index,
  • SPI is the Schedule Performance Index.