KPlato/Manual/Project Performance View: Difference between revisions

From KDE UserBase Wiki
(Created page with "==Description== The Project performance view is a project management chart where can be understood the actual situation of the project according the Earned Value Method. [[Image...")
(No difference)

Revision as of 13:31, 5 November 2010

Description

The Project performance view is a project management chart where can be understood the actual situation of the project according the Earned Value Method.

where:

  • BCWS means Budgeted Cost Work Scheduled,
  • BCWP means Budgeted Cost Work Performed,
  • ACWP means Actual Cost Work Performed.

All these are considered as effort in hours and costs.

PI are the Performance Indexes, where:

  • CPI is the Cost Performance Index,
  • SPI is the Schedule Performance Index.