Plan/Manual/Resource Assignment View: Difference between revisions
Appearance
Created page with "{{Construction}} ==Description== The Resource Assignemnt View displays the scheduled task-resource assignments. Image:Plan_resourceassignmentview.png|frame|right|350px|Gant..." |
mNo edit summary |
||
| Line 29: | Line 29: | ||
{| | {| | ||
| Using the context menu, the view can be configured using the configure dialog. | | Using the context menu, the view can be configured using the configure dialog. | ||
The configure dialog enables you include or exclude assignments. | The configure dialog enables you to include or exclude assignments. | ||
|[[Image:Plan_resourceassignmentview_config.png|frame|350px|Configuration Dialog]] | |[[Image:Plan_resourceassignmentview_config.png|frame|350px|Configuration Dialog]] | ||
|} | |} | ||
Revision as of 09:16, 22 February 2018
Description
The Resource Assignemnt View displays the scheduled task-resource assignments.
Data
The following columns are displayed as default:
| Column | Description |
| Name | The name of the object (Resource group, resource, task) |
| Total | The total assignemnet for a resource |
| Dates | The total assignemnts for a resource per day and the assigmnets for the resource per task. |
Editing data
The tasks description and progress can be edited using the context menu.
Configuration
| Using the context menu, the view can be configured using the configure dialog.
The configure dialog enables you to include or exclude assignments. |