Translations:Plan/Engineering To Order project tutorial/planning/112/en: Difference between revisions
Appearance
Importing a new version from external source |
(No difference)
|
Latest revision as of 08:40, 11 April 2019
If distribution is 'None', the tasks estimate is used as is during scheduling. If distribution is 'PERT', the estimate (E) used is calculated based on the entered optimistic- (O), pessimistic-(P) and most likely (M) estimate. The formula used for this is: