Description
The Resource Editor is used to create, edit, and delete resources and resource groups. Resources must belong to a resource group. At the moment sub-groups are not allowed. |
Working resources must refere to a calendar that defines the working hours for the resource. Calendars are created using the Work and Vacation Editor.
Material resources is by default always available. You can use a calendar to limit its availability.
Resources can be Shared or Local. A local resource is only used in the current project. A shared resource can be shared between multiple projects and is stored in a separate file, see Managing Resources.
Toolbar
The toolbar provides the means to create and delete resources and resource groups:
Button | Short cut | Description |
Add Resource Group | Ctrl+I | Button to create a resource group. The new group is appended at the end of the groups. |
Add Resource | Ctrl+Shift+I | Button to create a resource. The new resource is appended as a child to the currently selected group. If a resource is selected, the new resource is appended to its parent group. |
Delete | Delete | Deletes the selected resources and/or resource groups. |
Resources can be created by dropping data from any application that supports dragging vCard information, like KAddressBook or Evolution.
Resources can be copied or moved to a different resource group using drag-and-drop.
Editing data
Data can be edited inline as described here. Resources can also be edited using the resource settings dialog.
The following columns are displayed as default:
Column | Description |
Name | The name of the resource or resource group. |
Scope | A resource can be Shared or Local. A shared resource cannot be editied. |
Type | The type of the resource or resource group. |
Initials | The initials of the resource. |
The e-mail address of the resource. | |
Calendar | The calendar defines when the resource is working. |
Limit (%) | The maximum load that can be assigned. |
Available From | Defines when the resource is available to the project. |
Available Until | Defines when the resource is available to the project. |
Normal Rate | The cost pr hour, normal hours. |
Account | The account where the resource cost is accumulated. |
Configuration