Plan/Manual/Task Execution View: Difference between revisions
Appearance
mNo edit summary |
m Fix minor typos |
||
| Line 1: | Line 1: | ||
==Description== | ==Task Execution View== | ||
===Description=== | |||
{| | {| | ||
|The Task Execution View is used to inspect task performance information. | |The Task Execution View is used to inspect task performance information. | ||
| Line 5: | Line 7: | ||
|} | |} | ||
=Data= | ===Data=== | ||
{| | {| | ||
|Progress information can be edited in-line as described [[Plan/Manual/Using the Views|here]] or by using the task progress dialog. | |Progress information can be edited in-line as described [[Plan/Manual/Using the Views|here]] or by using the task progress dialog. | ||
| Line 58: | Line 60: | ||
|} | |} | ||
{{Plan/Prevnext|prevpage=Task Status View|indextext=Contents|nextpage=Task Gantt View}} | {{Plan/Prevnext|prevpage=Task Status View|indextext=Contents|nextpage=Task Gantt View}} | ||
[[Category:Office]] | [[Category:Office]] | ||
Revision as of 10:33, 1 November 2019
Task Execution View
Description
| The Task Execution View is used to inspect task performance information. |
Data
| Progress information can be edited in-line as described here or by using the task progress dialog. |
The following columns are displayed as default:
| Column | Description |
| Name | The name of the task. |
| Status | Task status |
| % Completed | Task completion |
| Responsible | The person responsible for this task. |
| Assignment | The resources assigned to this task. |
| SPI | Schedule Performance Index. (BCWP / BCWS) |
| BCWS | Budgeted Cost of Work Scheduled. |
| BCWP | Budgeted Cost of Work Performed. |
| ACWP | Actual Cost of Work Performed. |
| Description | Task description |
Configuration
Using the context menu, the view can be configured to show / hide the Project, split / unsplit the tree view or it can be configured using the configure dialog.
| The configure dialog enables you to tailor the amount of information the view displays to fit your needs. |