Plan/Manual/Creating ODT Report Templates: Difference between revisions
mNo edit summary |
mNo edit summary |
||
Line 1: | Line 1: | ||
{{Construction}} | {{Construction}} | ||
==Description== | ==Description== | ||
ODT report templates are regular odt files that can be designed using any odt word processor like ''Calligra Words'' or ''LibreOffice Writer''. The technique used is to use variables to hold references to the information that shall be fetched from the project. The variables are called ''User Fields'' in ''Writer'' and can be found under <menuchoice>Insert->Field->More Fields->Variables->User Fields</menuchoice>. In ''Words'' they are called ''Custom Variables'' and can be found | ODT report templates are regular odt files that can be designed using any odt word processor like ''Calligra Words'' or ''LibreOffice Writer''. The technique used is to use variables to hold references to the information that shall be fetched from the project. The variables are called ''User Fields'' in ''Writer'' and can be found under <menuchoice>Insert->Field->More Fields->Variables->User Fields</menuchoice>. In ''Words'' they are called ''Custom Variables'' and can be found under <menuchoice>Text Editing docker->Variable->Custom</menuchoice>. | ||
==Variables== | ==Variables== | ||
Line 85: | Line 85: | ||
To create a table, place a variable just before a table in your template file. The variable name identifies the table and must start with '''table''', e.g. '''table1'''. | To create a table, place a variable just before a table in your template file. The variable name identifies the table and must start with '''table''', e.g. '''table1'''. | ||
The value of the variable is used to point to the data to be fetched and must be one of the supported tables listed above, e.g '''taskstatus'''. | The value of the variable is used to point to the data to be fetched and must be one of the supported tables listed above, e.g '''taskstatus'''. | ||
You | You then put variables inside the table cells with name and value from the table below. | ||
<br/>Note that the schedules table supports the values | <br/>Note that the schedules table supports the values described in Shedule Values above. | ||
<br/>The projects, tasks and taskstatus tables supports the following values: | <br/>The projects, tasks and taskstatus tables supports the following values: | ||
Line 96: | Line 96: | ||
|- | |- | ||
| '''''table name'''''.name || Name || The name of the task or project | | '''''table name'''''.name || Name || The name of the task or project | ||
|- | |||
| '''''table name'''''.wbscode || WBS Code || | |||
|- | |- | ||
| '''''table name'''''.type || Type || Type of task | | '''''table name'''''.type || Type || Type of task | ||
Line 144: | Line 146: | ||
|- | |- | ||
| '''''table name'''''.endtime || End Time || | | '''''table name'''''.endtime || End Time || | ||
|- | |||
| '''''table name'''''.duration || Duration || | |||
|- | |- | ||
| '''''table name'''''.earlystart || Early Start || | | '''''table name'''''.earlystart || Early Start || | ||
Line 164: | Line 168: | ||
|- | |- | ||
| '''''table name'''''.assignaments || Assignments || | | '''''table name'''''.assignaments || Assignments || | ||
|- | |- | ||
| '''''table name'''''.variancedur || Variance (Dur) || | | '''''table name'''''.variancedur || Variance (Dur) || | ||
Line 194: | Line 196: | ||
|- | |- | ||
| '''''table name'''''.finished || Finished || | | '''''table name'''''.finished || Finished || | ||
<!-- | |||
|- | |- | ||
| '''''table name'''''.statusnote || Status Note || | | '''''table name'''''.statusnote || Status Note || | ||
--> | |||
|- | |- | ||
| '''''table name'''''.schedulingstatus || Scheduling Status || | | '''''table name'''''.schedulingstatus || Scheduling Status || | ||
Line 214: | Line 216: | ||
|- | |- | ||
| '''''table name'''''.schedulingerror || Scheduling Error || | | '''''table name'''''.schedulingerror || Scheduling Error || | ||
<!-- | |||
|- | |- | ||
| '''''table name'''''.level || Node level", "Level || | | '''''table name'''''.level || Node level", "Level || | ||
--> | |||
|- | |- | ||
| '''''table name'''''.bcws || Budgeted Cost of Work Scheduled", "BCWS || | | '''''table name'''''.bcws || Budgeted Cost of Work Scheduled", "BCWS || | ||
Line 229: | Line 230: | ||
|- | |- | ||
| '''''table name'''''.cpi || Cost Performance Index", "CPI || | | '''''table name'''''.cpi || Cost Performance Index", "CPI || | ||
|- | |- | ||
| '''''table name'''''.critical || Critical || | | '''''table name'''''.critical || Critical || | ||
|- | |- | ||
| '''''table name'''''.criticalpath || Critical Path || | | '''''table name'''''.criticalpath || Critical Path || | ||
<!-- | |||
|- | |- | ||
| '''''table name'''''.owner || Owner || | | '''''table name'''''.owner || Owner || | ||
Line 240: | Line 242: | ||
|- | |- | ||
| '''''table name'''''.time || Time || | | '''''table name'''''.time || Time || | ||
--> | |||
|} | |} | ||
Revision as of 13:14, 3 February 2018
Description
ODT report templates are regular odt files that can be designed using any odt word processor like Calligra Words or LibreOffice Writer. The technique used is to use variables to hold references to the information that shall be fetched from the project. The variables are called User Fields in Writer and can be found under
. In Words they are called Custom Variables and can be found under .Variables
Translated Labels
Translated lables enables us to produce general report templates that can be used in different languages.
Variable Name | Variable Value |
tr.project | Project |
tr.manager | Manager |
tr.schedule | Schedule |
tr.bcws | BCWS |
tr.bcwp | BCWP |
tr.acwp | ACWP |
tr.spi | SPI |
tr.cpi | SPI |
Project Values
Variable Name | Variable Value | Description |
project.name | Name | The name of the project |
project.manager | Manager | The name of the project manager |
project.bcwscost | BCWS Cost | Cost based Budgeted Cost of Work Scheduled |
project.bcwpcost | BCWP Cost | Cost based Budgeted Cost of Work Performed |
project.acwpcost | ACWP Cost | Cost based Actual Cost of Work Performed |
project.spicost | SPI Cost | Cost based Schedule Performance Index |
project.cpicost | CPI Cost | Cost based Cost Performance Index |
project.bcwseffort | BCWS Effort | Effort based Budgeted Cost of Work Scheduled |
project.bcwpeffort | BCWP Effort | Effort based Budgeted Cost of Work Performed |
project.acwpeffort | ACWP Effort | Effort based Actual Cost of Work Performed |
project.spieffort | SPI Effort | Effort based Schedule Performance Index |
project.cpieffort | CPI Effort | Effort based Cost Performance Index |
Schedule Values
Shows values from current schedule.
Variable Name | Variable Value | Description |
schedule.name | Name | The name of the schedule |
schedule.state | State | Scheduling state |
schedule.direction | Name | Scheduling direction |
Todo | The rest | of the values |
Tables
Supported tables:
- projects
- tasks
- taskstatus
- schedules
To create a table, place a variable just before a table in your template file. The variable name identifies the table and must start with table, e.g. table1. The value of the variable is used to point to the data to be fetched and must be one of the supported tables listed above, e.g taskstatus. You then put variables inside the table cells with name and value from the table below.
Note that the schedules table supports the values described in Shedule Values above.
The projects, tasks and taskstatus tables supports the following values:
Variable Name | Variable Value | Description |
table name.name | Name | The name of the task or project |
table name.wbscode | WBS Code | |
table name.type | Type | Type of task |
table name.responsible | Responsible | |
table name.allocation | Allocation | |
table name.estimatetype | Estimate Type | |
table name.calendar | Calendar | |
table name.estimate | Estimate | Most likely estimate |
table name.optimistic | Optimistic | Optimistic ratio |
table name.pessimistic | Pessimistic | Pessimistic ratio |
table name.risk | Risk | Risk type |
table name.constraint | Constraint | Type of time constraint |
table name.constraintstart | Constraint Start | |
table name.constraintend | Constraint End | |
table name.runingaccount | Running Account | |
table name.startupaccount | Startup Account | |
table name.startupcost | Startup Cost | |
table name.shutdownaccount | Shutdown Account | |
table name.shutdowncost | Shutdown Cost | |
table name.description | Description | |
table name.expected | Expected | |
table name.varianceest | Variance (Est) | |
table name.optimistic | Optimistic | |
table name.pessimistic | Pessimistic | |
table name.starttime | Start Time | |
table name.endtime | End Time | |
table name.duration | Duration | |
table name.earlystart | Early Start | |
table name.earlyfinish | Early Finish | |
table name.latestart | Late Start | |
table name.latefinish | Late Finish | |
table name.positivefloat | Positive Float | |
table name.freefloat | Free Float | |
table name.negativefloat | Negative Float | |
table name.startfloat | Start Float | |
table name.finishfloat | Finish Float | |
table name.assignaments | Assignments | |
table name.variancedur | Variance (Dur) | |
table name.optimisticdur | Optimistic (Dur) | |
table name.pessimisticdur | Pessimistic (Dur) | |
table name.status | Status | |
table name.completion | % Completed | |
table name.plannedeffort | Planned Effort | |
table name.actualeffort | Actual Effort | |
table name.remaningeffort | Remaining Effort | |
table name.plannedcost | Planned Cost | |
table name.actualcost | Actual Cost | |
table name.actualstart | Actual Start | |
table name.started | Started | |
table name.actualfinish | Actual Finish | |
table name.finished | Finished | |
table name.schedulingstatus | Scheduling Status | |
table name.notscheduled | Not Scheduled | |
table name.assignmentmissing | Assignment Missing | |
table name.resourceoverbooked | Resource Overbooked | |
table name.resourceunavailable | Resource Unavailable | |
table name.constrainterror | Constraints Error | |
table name.effortnotmet | Effort Not Met | |
table name.schedulingerror | Scheduling Error | |
table name.bcws | Budgeted Cost of Work Scheduled", "BCWS | |
table name.bcwp | Budgeted Cost of Work Performed", "BCWP | |
table name.acwp | Actual Cost of Work Performed", "ACWP | |
table name.spi | Schedule Performance Index", "SPI | |
table name.cpi | Cost Performance Index", "CPI | |
table name.critical | Critical | |
table name.criticalpath | Critical Path |
Projects Table
Task Status Table
Use by placing a variable with name tableX (X=number) with value taskstatus before the table that shall be filled in. Create a table with an optional header. The header can optionally contain variables. Fill the first row of the table with variables refers the values you want to fetch from the tasskstatus table.
The variable has this format:
Variable: Name: tableX.<column> (X=number) Value: taskstatus
where <column> is a column name
Example: A table with header. The header fetches column names from the taskstatus table.
Variable: Name: table1 Value: taskstatus
Variable Name: table1.name Value: Name
|
This is the header so fetches the header of the column |
Variable Name: table1.name Value: Name |
This is the values so fetches the actual column value |
Tasks Table
Chart
Use by placing a variable with name chartX (X=number) with value project before the chart that shall be used.
The variable has this format:
Variable: Name: chartX (X=number) Value: project; values=data;
where data is a comma separated list of values to be include in the chart.
Possible values are:
- bcws effort Budgeted cost of work scheduled, effort based.
- bcwp effort Budgeted cost of work performed, effort based.
- acwp effort Actual cost of work performed, effort based.
- spi effort Schedule performance index, effort based.
- cpi effort Cost performance index, effort based.
- bcws cost Budgeted cost of work scheduled, cost based.
- bcwp cost Budgeted cost of work performed, cost based.
- acwp cost Actual cost of work performed, cost based.
- spi cost Schedule performance index, cost based.
- cpi cost Cost performance index, cost based.
Gantt
Not supported.