Translations:Plan/Engineering To Order project tutorial/planning/10/en

From KDE UserBase Wiki
Revision as of 08:40, 11 April 2019 by FuzzyBot (talk | contribs) (Importing a new version from external source)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)

The target times Earliest start and Latest finish are used when scheduling the project. We want to schedule forward, so we set earliest start to when we want the project to start, and the latest finish we set to the latest time the project should finish. If the project cannot be scheduled to finish before this time, a scheduling warning will be given.