Translations:Plan/Engineering To Order project tutorial/planning/112/en

From KDE UserBase Wiki
Revision as of 08:40, 11 April 2019 by FuzzyBot (talk | contribs) (Importing a new version from external source)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)

If distribution is 'None', the tasks estimate is used as is during scheduling. If distribution is 'PERT', the estimate (E) used is calculated based on the entered optimistic- (O), pessimistic-(P) and most likely (M) estimate. The formula used for this is: