Plan/Manual/Task Status View
Appearance
Description
| The Task Status View is used to inspect task progress information at a period, set in the configuration. |
The tasks are divided into groups dependent on the status of the task:
| Not Started | Tasks that should have been started by now. |
| Running | Tasks that have been started, but not yet finished. |
| Finished | Tasks that were finished in this period |
| Next Period | Tasks that are scheduled to be started in the next period. |
Editing data
| Progress information can be edited in-line as described here or by using the task progress dialog. |
The following columns are displayed as default:
| Column | Description |
| Name | The name of the task. |
| Status | Task status |
| % Completion | Task completion |
| Planned Effort | The amount of work planned to be used at the end of the current period. |
| Actual Effort | The amount of work spent. |
| Remaining Effort | The remaining effort needed to complete the task. |
| Planned Cost | The planned cost at the end of the current period. |
| Actual Cost | The actual cost incurred. |
| Actual Start | The actual start time of the task. |
| Actual Finish | The actual finish time of the task. |
Configuration
Using the context menu, the view can be configured to split / unsplit the tree view or it can be configured using the configure dialog.
| The configure dialog enables you to tailor the amount of information the view displays to fit your needs. |