Revision as of 08:18, 20 September 2010 by Dag(talk | contribs)(Created page with '{{Construction}} ==Description== {| |The Task Execution View is used to inspect task performance information. ||250px|thumb |} =Data= {| |...')
The Task Execution View is used to inspect task performance information.
Data
Progress information can be edited in-line as described here or by using the task progress dialog.
The following columns are displayed as default:
Column
Description
Name
The name of the task.
Status
Task status
% Completed
Task completion
Responsible
The person responsible for this task.
Assignment
The resources assigned to this task.
SPI
Schedule Performance Index. (BCWP / BCWS)
BCWS
Budgeted Cost of Work Scheduled.
BCWP
Budgeted Cost of Work Performed.
ACWP
Actual Cost of Work Performed.
Description
Task description
Configuration
Using the context menu, the view can be configured to show / hide the Project, split / unsplit the tree view or it can be configured using the configure dialog.
The configure dialog enables you to tailor the amount of information the view displays to fit your needs.